Eastcombe

Download our Factsheet
View of drilling rig on road

Project Summary

CC Ground Investigations Ltd were engaged as Principal Contractor to carry out a site investigation within the road and adjacent third-party land. The road is currently closed to traffic due to ground movement affecting the carriageway.

The purpose of the contract was to establish ground and groundwater conditions at the site, characterise the ground movements affecting the carriageway, and to install monitoring equipment to measure any ground movements and to assist with the design of future remediation of the slope.

Project Details

A Fraste multi-purpose drilling rig was used on the road to obtain cores of the underlying rock, and a Modular Terrier drilling rig was used for investigation on the slope within an orchard.

The boreholes on the road were installed with 70mm diameter inclinometer pipe, and the modular boreholes installed with slip indicators.

All works were supervised on a full-time basis by suitably qualified in-house Engineering Geologists.

Geotechnical logging was carried out to BS5930: 2015+A1:2020, BS EN ISO 14688 [Parts 1 and 2] and BS EN ISO 14689 with detailed discontinuity spacing records and particular care to record any zones of weakness/possible zones of movement.

The program of works included:

  • GPR service tracing
  • 2 No service slit trenches
  • 4 No Multipurpose combined dynamic sampling and rotary coring boreholes
  • 7 No Windowless Modular dynamic sampling boreholes
  • 1 No 50mm ground water monitoring standpipe
  • 3 No Inclinometer instruments
  • 6 No slip indicators
  • In-situ testing including SPTs and hand shear vanes
  • Geotechnical and geo-environmental laboratory testing
  • Factual reporting
Download our Factsheet
Related Case Studies
Eastern Green Link is one of several developments required to increase the capability of the transmission network from the North-East of Scotland to the North of England. The increase is required to facilitate the growth in flows of renewable energy generation in the North to centres of demand in the South; helping to ensure the UK can meet its target of enabling 40GW of renewable energy by 2030 and achieving a ‘Net Zero economy’ by 2050.
A ground investigation was required to provide geotechnical and geo-environmental data for the design and installation of a new canopy outside of a high rise building in central London.
Ground investigation to provide geotechnical and geo-environmental data for the upgrade of an existing water treatment works.