A ground investigation was required to provide geotechnical data and geoenvironmental for the design of a replacement water treatment works.

Project Details:

Six exploratory locations were carried out using a CCGI Cable Percussion rig, hand pits and a machine excavated trial pit.

The program of works included:

  • CCGI providing engineering services
  • 3 No Cable Percussion boreholes to 10m in glacial till
  • In-situ testing including SPTs
  • 2 No Test pits
  • 1 No machine excavated trial pit
  • Installation of gas and ground water monitoring standpipes
  • Return visits to monitor standpipes for gas and ground water.
  • Geotechnical and geoenvironmental laboratory testing.
  • Factual Reporting

Project Details

Download our Factsheet
Related Case Studies
Eastern Green Link is one of several developments required to increase the capability of the transmission network from the North-East of Scotland to the North of England. The increase is required to facilitate the growth in flows of renewable energy generation in the North to centres of demand in the South; helping to ensure the UK can meet its target of enabling 40GW of renewable energy by 2030 and achieving a ‘Net Zero economy’ by 2050.
A ground investigation was required to provide geotechnical and geo-environmental data for the design and installation of a new canopy outside of a high rise building in central London.